Opening the Resource Pool Manager
Select Tools->Resource Editor and the Resource Pool Manager will be presented. The Resource Pool Editor allows you to create and manage the entries and attributes of the resources that are contributing to your project.
Resource may be either people, materials (expendable), or equipment.
The one shown already has a few resources in place - yours will be blank when first opened.
Resource Pool Manager Properties
Name A resource name Text describing a resource.
Short name Letters and number. Initials, nick name, or some other identifier for the resource.
Type People, equipment, material Resource classification.
Email Resource email address An email address for the resource of the form Someone@somewhere.com.
Max. Units A percentage The percentage of the total time available from this resource that may be applied to this project.
Std. Rate Monetary units The standard daily rate applicable to this resource.
Ovt. Rate Monetary units The overtime daily rate applicable to this resource.
Cost/Use Monetary units A fixed daily cost associated with each use of this resource.
Accrue At When should the income for this resource be taken.
Start: income taken when the task is begun.
End: income taken when the task is complete.
Prorated: income is taken as the task proceeds. (i.e., 25% payment when the task is 25% complete).
Note Information further describing the resource.
If you are using SharedPlan Pro and have a SharedPlan Central account with resources and resource packages created the Import... and Import Package... buttons will all you to load them into your project.